The equipment recipe on articles

How to define on an article which equipment is needed and for how long (the “recipe”), so that it is booked automatically when the article is used in an order.

The equipment recipe is the way to say, once and for all, which equipment an article needs and when. Set on the article, it makes it so that, when you plan the operators on an activity that uses that article, the equipment books itself at the corresponding times — without having to assign it by hand order by order.

It is particularly useful for services that always require the same machines: for example a “Haul-out” that uses the crane at the start and the cradle for the whole duration, or a “Launch” that commits the crane only for the last half hour.

Where to set it

  1. Open Settings → Prices lists, products and services → Products master data and choose the article.

  2. In the top band of the record press Equipment usage. You need the permission Products → Update.

  3. The Equipment usage page opens (with the article's name), with the explanation at the top: define which equipment is needed for this article and when, within the working window; when you plan the operators on an activity that uses this article, the equipment is booked automatically at the corresponding times.

Variants share the “parent” article's recipe. If the article has size variants, set the recipe on the main article: it applies to all its variants.

Adding equipment to the recipe

Fill in the row at the top and press Add. The fields are:

Field

What it is for

Equipment

The equipment required (choose from the list of the marina's equipment: they all appear).

Whole window

If ticked, the equipment is committed for the whole working window of the activity. It disables the other time fields.

Anchor

Where the equipment's window is measured from: From start or From end of the work.

Offset (min)

By how many minutes the commitment is shifted from the anchor.

Duration (min)

For how many minutes the equipment stays committed.

Quantity

How many units of the same equipment are needed at the same time.

The whole window, or only a part?

  • Whole window → the equipment is needed from the start to the end of the job (typical of the cradle, which holds the boat for the whole storage).

  • Only a stretch → untick “Whole window” and define the stretch with Anchor + Offset + Duration:

    • From start, offset 0, duration 30 → the first 30 minutes of the job (e.g. the crane for the initial lift).

    • From end, offset 0, duration 30 → the last 30 minutes (e.g. the crane for the final launch).

    • From start, offset 60, duration 45 → 45 minutes, starting one hour after the start.

The list of configured equipment

Under the form there is the table of what you have set:

Column

Content

Equipment

The equipment's name.

When

The window in words: “Whole window” or, e.g., “From start +60' · 45'” (starts 60 minutes after the start, lasts 45 minutes).

Quantity

The number of units.

Each row has a button to remove it (it asks for confirmation: “Remove this equipment from the recipe?”). If you have not configured anything yet, “No equipment configured yet.” appears.

What happens in orders

The bookings follow the operators' planning: if no operator is planned on an activity, nothing is booked. How it works and how to see the result is in Equipment in orders.

In short

  1. Set the recipe on the article (once).

  2. In orders, plan the operators on the activities that use that article.

  3. The equipment books itself, at the right time and in the right quantity.