The Board (Shipyard → Planning → Calendar and board, then Board) shows planning in rows: one row for each operator and one for each piece of equipment, with time running horizontally. It is the right view to understand who is busy and who is free and to move work between people.
How to read it
Each bar is an assignment (a job on an operator). On the bar you find the job number, the boat/work and a badge with the duration of work (e.g. 🕐 12:00).
The equipment rows show the bookings that come from the operators' work (they are read-only: they move following the operator).
An equipment's maintenance periods appear as yellow/grey striped bands on its row.
The greyed closed slots and the hidden closing days follow the schedules: see Yard and operator schedules.
You can hide the left column to use the Board at full width.
Editing from the Board
Move a bar by dragging it through time (same operator) or onto another operator row to reassign it to another person.
Resize from the right edge to change the hours of work (see the article How long a job takes and how it is spread).
Click a bar to open the edit window; with the right click the menu offers Link to others, Unlink from group, Delete this one, Delete all for this activity and Go to this order.
Operators' absences appear as striped bands on their row (blue holiday, red sick leave, purple leave). Here too, when assigning a job, you can choose a Team.
Linking several jobs (they move together)
If several assignments must move together, you can link them into a group:
From the menu (right click), on the Calendar as on the Board, choose “Link to others”, select the activities to connect and press Link. From then on, when you move one, all of them move by the same amount of time.
Linked bars show a chain icon that signals the connection.
To detach one, use “Unlink from group”.
Note: only assignments of the same order can be linked.
Colours
As on the Calendar, you can colour the bars by work status, by article group or category; group and category colours are the ones set in the price list. The colour selector is available when you are not browsing the list of orders.
When to prefer the Board over the Calendar
To compare several operators (and the equipment) over the same period.
To quickly reassign work from one person to another.
For an overview of the whole yard. If instead you plan one order at a time looking at the day's slots, the Calendar is more convenient.