What they are for
Many jobs always follow the same sequence. A winter dry storage bundle, for example, almost always means: first the boat is hauled out, then the hull is washed, then the antifouling is applied and finally the boat is put on the hard.
Dependencies between articles let you draw this sequence once, inside the bundle. From then on, every time you add the bundle to an order, the sequence is recreated automatically between the order's jobs: you no longer have to link them by hand order by order.
A dependency is a directed link between two articles of the bundle: it says that one (the predecessor) comes first and the other (the successor) comes after.
The four types of link
Every dependency has a type, which specifies what must happen to the predecessor before the successor can start or finish. They are the same four types used in planning diagrams:
Type | Abbreviation | Meaning |
|---|---|---|
Finish to Start | FS | The successor can start when the predecessor has finished (the most common case). |
Start to Start | SS | The successor can start when the predecessor has started. |
Finish to Finish | FF | The successor can finish when the predecessor has finished. |
Start to Finish | SF | The successor can finish when the predecessor has started. |
The default type is Finish to Start, which covers most cases (“finish this, then start that”).
The lag (days)
To each dependency you can add a Lag (days): a number of days that pass between the two articles.
A positive lag spaces the two jobs apart. Example: antifouling → dry storage on the hard with a lag of +1, to let the paint dry for a day before putting the boat back on the hard.
The default lag is 0 (no wait).
Where to find them
Open Settings → Prices lists, products and services → Product bundles.
On the bundle's row press the View icon (the eye).
In the Actions tab, Bundle group, choose Article dependencies.
Boat sale bundles (the boat models) don't have this entry.
In the Drawing the dependencies we see how to link the articles in the editor.